Dates - Work Start Date, Ship Date, and Dock Date

Each order line carries three dates. Set them in the lines table on the order's screen; production, shipping and accounting all work from them.

Updated Nov 9 2026

Dates - Work Start Date, Ship Date, and Dock Date

Allow external media cookies to watch this video.

Before you start

DateWhat it meansWhat uses it
Dock DateWhen the customer needs the goods to arriveThe customer's due date
Ship DateWhen you plan to shipScheduling works back from it; the estimated A/R due date is the Ship Date plus the terms days
Work Start DateWhen production should start on a build lineWhen the work order is scheduled to start

Before you start

  • Editing order lines needs the Can Edit Order function (Sales, Manager or CanEditOrders role by default). Without it the lines can't be put into edit mode.
  • A closed order can't be edited.
  1. Set the dates on an order line

    1. Go to Sales > Orders > Order List (the page is headed Orders), find the order with the filter search bar (Filter or search…, for example Order #, then Apply (n)) and open it. Order numbers carry a suffix, for example 184.1.
    2. In the order's lines table, click the pencil icon (Edit orderline) on the line; scroll the table sideways if you can't see it. Its Work Start Date, Ship Date and Dock Date become date boxes.
    3. Enter the Ship Date you'll ship on first, then the Dock Date the customer asked for, and click outside the box.
    4. Click the check mark (Save) on the line. Cetec shows Ordline updated Succesfully. If you've changed several lines, SAVE ALL under the table saves them all (The order line(s) were updated successfully.).
  2. Let Cetec work out the Work Start Date

    1. On the order (Sales > Orders > Order List), click Edit orderline on a build line and change its Ship Date (the info icon beside it reads Changing the Ship Date will cause the Work Start Date to be recalculated.), quantity, part or revision, then save the line.
    2. Cetec recalculates the Work Start Date: it counts back from the Ship Date by the line's labor time (unit labor × quantity plus setup), the lead times on its labor plan and any buffer days, skipping non-working days.
    3. To fix the start date yourself, type it in Work Start Date and save the line. A typed date is locked from auto scheduling. The [+] beside the date box opens the line's schedule (Scheduled Start, Scheduled Finish, Schedule Locked?, Reschedule Forwards / Reschedule Backwards).
  3. Find orders by date

    1. Go to Production > Orders > Production Order List.
    2. Click the filter search bar (Filter or search…) and choose the date to filter on: Ship Date, Work Start Date, Dock Date or Ordered On Date (type Date to list them).
    3. Pick a preset (such as This month) or Choose a date, pick the start and end dates, then click Apply (n). The filter shows as a chip above the list, for example Ship Date is between 2026-12-01 – 2026-12-01.