How To Track Additional Labor and Material Cost in Inspection Failure Report
Charge rework time and scrapped material to the inspection failure that caused them, and see the cost of each failure on the Inspection Failures report.Updated Nov 9 2026
Before you start
- Inspection Failures is under Production > Quality. Recording inspections needs Can Edit Inspections (the User, Production, Quality or Quality Engineer role by default).
- Labor cost is time × the labor rate for the user or work location. With no labor rate set, Additional Labor stays $0.00.
-
Record the failure
- Open the work order (Production > Orders > Production Order List, then the order number) and click Inspections in its left-hand menu.
- Click Create Inspection, fill in the required fields with the Qty Rejected, and set Work Location and Inspector. Click Create.
- In Set Failure Details, pick the Failure code for each rejected piece and click Update. Each rejected piece becomes an inspection failure. (See How To Create an Inspection on an Open Order for every field.)
-
Charge rework labor to the failure
- On the work order (new Work view), click Start Work.
- In Failed Inspection, pick the failure the work is for.
- Click Start Work to time the rework, or enter the Duration under OR ADD TIME & CLOSE AT ONCE and click Submit. Cetec ERP shows Work record successfully created! The labor and overhead for that time are charged to the failure.
-
Charge scrapped material to the failure
Either request replacement parts as scrap, or scrap the finished assembly.
Replacement parts
- On the work order, open the Materials tab and click Req More on the part.
- In Request More Parts, enter the Qty, tick Request Is Due To Scrap?, set Reason to Failed Inspection, and pick the failure in Failed Inspection. Click Send. Cetec ERP shows Part Request Created (# n).
- Open the part request (View Part Request) and check its Failed Inspection is set; pick it and click Update if it's blank.
- When the warehouse picks it (Pick All, then Update Pick Parts), the picked value is charged to the failure.
Finished assemblies
- If only some of the finished units are scrapped, click Split Line on the work order and move them to their own line first.
- On the order, click CLOSE LINE/ALL, tick Delete on that line and click Delete Selected Lines.
- The window warns Parts picked on line(s) will be scrapped with a reason code. Pick the Reason Code (for example scrap) and the Failed Inspection, then click Confirm. The scrapped parts' cost is charged to the failure.
-
Review the cost
- Go to Production > Quality > Inspection Failures. It shows failures from the last 30 days by default.
- Scroll right: Additional Labor and Additional Material show what each failure cost.
- To trace scrapped components, go to Parts > Reports > Inventory Activity and filter for the component; its Failed Inspection column shows the failure it was scrapped against.