Order Processing - Outsource PO
Send a step of a job, such as plating, heat treating or anodizing, to an outside processor. Set up the outsourcing work location, the vendor and a service part once; then raise an outsource PO from each work order that needs it, so the PO is tied to the job and its cost.Updated Nov 9 2026
Before you start
- Data Maintenance (Admin > Maintenance) needs the Admin role or the Can Edit Maintenance function.
- Creating vendors, PRCs and parts needs the usual purchasing and engineering permissions; see the guides linked below.
- Editing a labor plan needs the Can Edit Revisions function (Manager, Doc Control or Engineer by default).
-
Set up the outsourcing work location
Do this once per kind of outside work. Your system may already have one, such as At Vendor Outsourcing.
- Go to Admin > Maintenance > Data Maintenance. Click the filter search bar (Filter or
search…), choose Data Type, type
OrdlineStatusand click Apply (1). - Click OrdlineStatus. The page Data Maintenance For OrdlineStatus lists your work locations.
- Click Add Record. Cetec saves an empty row at once. Fill in its Description, for example Outsourced - Plating.
- Tick Is Outsourcing on the row (scroll right to find it). This marks the location as work done outside your building.
- Fill in anything else your shop uses, then click Submit.
- Go to Admin > Maintenance > Data Maintenance. Click the filter search bar (Filter or
search…), choose Data Type, type
-
Set up the vendor and the service part
- Create the processor as a vendor: Purchasing > Vendors > Vendor List, Create, type the Vendor Name and click Create. See How To Create a Vendor.
- Decide which PRC (product code) the service parts go under. The outsource PO uses the first three characters of the part number as its PRC, so the PRC must exist. To add one, go to Parts > Lists > PRC List and click Create PRC (see How To Create a PRC (Product Code)). To make its parts non-inventory, point at the PRC's row on the PRC List, click the pencil (Edit PRC) and tick Default as Non-Inventory; the Create PRC window doesn't have that box.
- Create the service part: Parts > Lists > Part List (the page is headed Parts), Create Part, choose the PRC, type the Part number and a Part Description, check the Location, and click Create. See How To Create Non-Inventory Parts.
-
Add the outsourcing step to the labor plan
- Go to Parts > Lists > Part List and click the BOM's part number in the PrcPart column.
- Click Revisions in the part's left menu, and on the revision's row click Labor Plan.
- Choose the outsourcing work location in the Search ordline status (location)... box under the table and click Add. Cetec shows Successfully added the location.
- On that location's row, type the processor's turnaround in Outsource Lead Time (in days) and click Update. Cetec uses it to back out the work start date.
- Drag the row by its handle to where the step happens in the routing. See How To Create a Labor Plan (Traveler) for the rest of the labor plan.
-
Create the outsource PO
- Open the work order: go to Production > Orders > Production Order List and click the order line. The work order screen opens.
- Click Outsource PO in the work order's header. The Outsource PO screen opens in a new tab and lists any outsource POs the work order already has.
- In Create new PO for Vendor, search for the processor and pick it. The Location is the work order's own. To add a line to an outsource PO you already have, fill in OR add to PO instead.
- Under Add Line, search for the service part in Prcpart and pick it (the grey Welding and 1.99 in the boxes are only examples). Cetec fills in the Cost a moment later and puts the part's description in Comments.
- Check the Cost. Dock Date can be left empty for today. Qty starts at 1; tick Lock Qty To Line to make it the work order's quantity (the box then can't be changed).
- Type any Comments for the processor, after picking the part so they aren't overwritten. They print on the PO.
- Click Create Outsource PO. Cetec places the PO straight away (there is no draft) and shows PO n Created! with the PO number, for example PO 207.1 Created! The PO is listed at the top of the screen. Like any new PO it may show Pending Approval until it is approved.
If Cetec shows No Vendor Chosen, No Prcpart Entered or PRC does not exist, please try again, fix that field and click again. If it says You must have a cost center on this line to make an Outsource PO, your company requires a cost center on the order line; set one first.
-
Send the work and track it
- On the work order, click Move Location. In the Move Location window, pick the outsourcing work location from the Location drop-down and click Move, so the shop can see the job is out. The drop-down shows only the work order's own routing steps; click See All beside it if the outsourcing location isn't there (for example, a work order made before you changed the labor plan). See All shows only if you're allowed to change location groups.
- Open the PO from the PO # link on the Outsource PO screen. The PO shows Outsource PO For Order and the order number, and its left-hand menu has an ORDER link back to the order.
- In the PO's left-hand menu, click Packing Slip to print a packing slip for the material you send (Download PDF), and PDF/Email to send the PO (Email PO).
- To see every outsource PO on an order, open the order, click BUILD/BUY + in its left-hand menu, then OUTSOURCE POS (n) and VIEW ALL. On the Purchase Order List, the Type filter set to Outsource lists all of them.
- When the work comes back, receive the PO line like any other. Outsource PO costs go into the order's cost, and an outsource PO that hasn't been received is received automatically when the order is completed (invoiced).