Order Processing - Perform a Part Request
When the shop floor needs more parts for a job (scrap, a build error, a short kit), request them from the work order. The warehouse then picks the parts to the request, delivers them and closes it, so the extra material is recorded against the job with a reason.Updated Nov 9 2026
Before you start
- Making part requests needs the Can Access Part Requests function (Manager, Supervisor, Part Request or Production Only role by default). Without it Cetec ERP shows Permission Denied, Part Request Prohibited.
- The Reason list comes from your company's part request reasons (PartRequestReason in Admin > Maintenance > Data Maintenance). Each reason must be linked to an inventory change type, or picking fails. The default reasons are Scrap, Build Error, Destructive Test, Missing Part and Failed Inspection.
- If your company sets part request approval thresholds, requests above the threshold wait for approval before they can be picked.
-
Request more parts from the work order
- Open the work order (Production > Orders > Production Order List, click the number in the Order column).
- Open the work order's parts list: click the Materials tab at the top of the Work page, or Parts > View All Parts in the left menu (which you see depends on your company's work order menu).
- Find the part and click Req More in its Request Parts column. The Request More Parts window opens with the part filled in. You can only request parts on the job's BOM or the line's own part; click + to add more parts.
- Enter the Qty you need.
- Tick Request Is Due To Scrap? if the parts were scrapped, and pick the Reason.
- Add Comments and click Send. Cetec ERP shows Part Request Created (# n).
-
Pick the parts to the request
- Go to Production > Part Request List. It shows open requests.
- Click the number in the Req # column. The request opens.
- Check the Part, Qty Requested, Order, Request Reason and Request Comments.
- In the bin list, enter how many you take from each bin in Qty Picked, or click Pick All on a bin.
- Click Update Pick Parts. The picked parts now show on the work order's Pick Parts as picked (shown in orange when they exceed the original need).
-
Deliver and close the request
- Take the parts to whoever asked for them.
- On the request, click the status at the top right (for example Approved/Pending Pick). The status menu lists the stages the request can move to.
- Click Pick Complete And Closed. Use Pick Complete/Pending Delivery instead if someone else is delivering the parts, and close the request later.