Gather the material a job needs.

Updated Nov 5 2026

Who this is for

Pickers gather the parts a work order needs and hand them to the floor. Production waits on the kit, and supervisors decide which jobs are picked first.

Applies to
Inventory
Production

Why it matters: picking is where parts leave stock and become work in progress. A job picked short stops on the floor; parts picked but not recorded leave the shelf count wrong and the job's cost incomplete.

  1. Open your pick queue

    1. Open Warehouse > Release To Production > Pick Queue. Under Your orders it lists the work orders released to you, grouped by work location.
    2. Hover over the next work order's row and click Pick at its right-hand end. The work order's Pick Parts screen opens.
    3. The pick list prints on the work order's license plate by default. To print it on its own, click Documents on the work order and open Part Pick List.
  2. Pick the parts

    1. On the work order's Pick Parts screen, find each component. Qty Need shows how many the job needs, and the bins that hold it are listed underneath.
    2. Take the parts from the shelf and type how many you took from each bin. The box holds the total picked from that bin so far, not an amount to add. For a serialized part, Cetec asks for the serial numbers you picked instead of a quantity. Picking only part of a bin asks you to confirm Splitting Bin! PO Traceability may be impacted. Cetec stops you picking more than a bin holds: Quantity {n} exceeds bin qty, setting to {qty}.
    3. Check the colours: green means the component is fully picked, blue means part-picked, and orange means more than the job needs. Picking more than the job needs only turns the line orange, unless your company forbids overpicking.
    4. Click Update. Cetec shows Part Pick Recorded. To go straight to your next job, click Update, Go To Pick Queue instead (it reads Update, Go To Order List if your default location isn't the warehouse).
  3. Send the job to its next step

    1. At the bottom of the Pick Parts screen, choose the next location in Set Workorder Location To (the list is not in routing order).
    2. Click Update.
    3. The work order moves to that location, so the floor can see the kit is ready.
  4. Return parts you picked

    1. On the work order, click Dekit Parts in the left-hand menu.
    2. Type how many of each part to put back in Return Qty, and check the Return Bin (left blank, Cetec returns them to the bin shown in grey).
    3. Click Update. Cetec shows Dekit Successful. To put back everything picked for the line, click Dekit Line {n}.

Other ways to do this

Pick every line at once

On the Pick Parts screen, Pick All Lines picks every component to its full need from the bins Cetec chooses. Your company can hide it.

Get more parts after scrap or damage

If the floor needs more parts because some were scrapped or damaged, they raise a part request instead. See Replace material on a job.