Schedule the shop
Turn open demand into a plan the shop can run.Updated Nov 5 2026
Who this is for
Schedulers and production managers turn open build orders into a plan the shop can run: each job laid against the hours each work location has, so they can see when it will really start and finish. Giving a customer a delivery date, and rebuilding the plan when a machine goes down or material slips, are separate jobs that start from this plan.
Applies to
Why it matters: a plan that ignores what else is on the floor can't be run. Scheduling against capacity shows which orders will be late while there is still time to act.
-
Schedule the work order
- Open the work order and go to its Schedule: the
SCHEDULEtab on the older Work view, or theScheduleitem in the left-hand menu on the newer one. - Click
Reschedule Forwardsto schedule from the Work Start Date, orReschedule Backwardsto schedule back from the Ship Date. Confirm Update Production Schedule Now?Reschedule Forwardsstarts from the Work Start Date even if it is in the past. If there is no Work Start Date, it starts today. - Compare Scheduled Finish with the Ship Date, and Scheduled Start with the Work Start Date. A date that misses is highlighted: hover it for After Order Line Ship Date! or Before Order Line Work Start Date!. Those orders won't make their dates as scheduled.
- Set the
Priority Rank(higher numbers schedule first) and clickUpdate. Cetec saves it with no message. - To stop a batch reschedule moving this job, lock it: click
Lockon the older view, or tickSchedule Locked?and clickUpdateon the newer one. Schedule Locked? showsYesorNo; a locked line showsUnlockinstead ofLock. A locked line still moves when you clickReschedule ForwardsorReschedule Backwards, or drag it on the Gantt.
- Open the work order and go to its Schedule: the
-
See the load on the Gantt
- Open
Production > Scheduling > Planning Gantt Chart. The page is titled Production Scheduling Gantt Chart and starts at today. - Switch between
View By Order,View By Production LineandView By Locationto see where the load piles up. The order is on each row, or on the bar inView By Location. Hover a bar for its part, work location and the capacity it uses. - The chart shows one week. To see later work, scroll on the chart to zoom out, or change the dates at the top.
- Click
Show Unscheduled Linesto list orders not on the schedule. The button changes toHide Unscheduled Lines, and the Unscheduled Order Lines table appears below the chart.
- Open
-
Move the job or the date
- On the Gantt, click a bar to select it, then drag it to move it in time. Cetec saves it with no message.
- Or change the order's dates to match the schedule: on the Gantt, tick the box on each
order's row, click
Batch Update Dates, and chooseUpdate Work Start Date,Update Ship Dateor both. Only unlocked rows have a tick box; on a locked row, clickUnlock?first. If the window says No Orders Selected, no row is ticked. Cetec reloads the Gantt with no message. - Choose
Update Ship Dateonly for a date already agreed with the customer. Changing a ship date changes what the customer was promised.
Other ways to do this
Reschedule many orders at once
New orders have come in, or priorities have changed.
- Open
Production > Scheduling > Batch Reschedule. - Filter the list to the orders, and tick them. On the older screen the filters sit above the
list: set
Order Schedule LocktoUnlockedand clickSubmit. On the newer one, clickFiltersand setOrder TypetoUnlocked. The date filter starts at today, which hides lines that started earlier. - Click
Batch Reschedule, and chooseForward ScheduleorBackward Schedule. - Set the one date that direction uses. Both dates start at today, not at the lines' own dates.
Forward Schedulestarts every line on theWork Start Dateand sets its Ship Date to that date plus the line's labor days.Backward Schedulesets every line's Ship Date to theShip Dateand works the start back from it. - Click
Submit. Cetec shows Ordline schedule updated successfully and locks the lines. - Check the result on the work orders' Schedule, as in Schedule the work order.