Schedule the shop

Turn open demand into a plan the shop can run.

Updated Nov 5 2026

Who this is for

Schedulers and production managers turn open build orders into a plan the shop can run: each job laid against the hours each work location has, so they can see when it will really start and finish. Giving a customer a delivery date, and rebuilding the plan when a machine goes down or material slips, are separate jobs that start from this plan.

Applies to
Planning
Production

Why it matters: a plan that ignores what else is on the floor can't be run. Scheduling against capacity shows which orders will be late while there is still time to act.

  1. Schedule the work order

    1. Open the work order and go to its Schedule: the SCHEDULE tab on the older Work view, or the Schedule item in the left-hand menu on the newer one.
    2. Click Reschedule Forwards to schedule from the Work Start Date, or Reschedule Backwards to schedule back from the Ship Date. Confirm Update Production Schedule Now? Reschedule Forwards starts from the Work Start Date even if it is in the past. If there is no Work Start Date, it starts today.
    3. Compare Scheduled Finish with the Ship Date, and Scheduled Start with the Work Start Date. A date that misses is highlighted: hover it for After Order Line Ship Date! or Before Order Line Work Start Date!. Those orders won't make their dates as scheduled.
    4. Set the Priority Rank (higher numbers schedule first) and click Update. Cetec saves it with no message.
    5. To stop a batch reschedule moving this job, lock it: click Lock on the older view, or tick Schedule Locked? and click Update on the newer one. Schedule Locked? shows Yes or No; a locked line shows Unlock instead of Lock. A locked line still moves when you click Reschedule Forwards or Reschedule Backwards, or drag it on the Gantt.
  2. See the load on the Gantt

    1. Open Production > Scheduling > Planning Gantt Chart. The page is titled Production Scheduling Gantt Chart and starts at today.
    2. Switch between View By Order, View By Production Line and View By Location to see where the load piles up. The order is on each row, or on the bar in View By Location. Hover a bar for its part, work location and the capacity it uses.
    3. The chart shows one week. To see later work, scroll on the chart to zoom out, or change the dates at the top.
    4. Click Show Unscheduled Lines to list orders not on the schedule. The button changes to Hide Unscheduled Lines, and the Unscheduled Order Lines table appears below the chart.
  3. Move the job or the date

    1. On the Gantt, click a bar to select it, then drag it to move it in time. Cetec saves it with no message.
    2. Or change the order's dates to match the schedule: on the Gantt, tick the box on each order's row, click Batch Update Dates, and choose Update Work Start Date, Update Ship Date or both. Only unlocked rows have a tick box; on a locked row, click Unlock? first. If the window says No Orders Selected, no row is ticked. Cetec reloads the Gantt with no message.
    3. Choose Update Ship Date only for a date already agreed with the customer. Changing a ship date changes what the customer was promised.

Other ways to do this

Reschedule many orders at once

New orders have come in, or priorities have changed.

  1. Open Production > Scheduling > Batch Reschedule.
  2. Filter the list to the orders, and tick them. On the older screen the filters sit above the list: set Order Schedule Lock to Unlocked and click Submit. On the newer one, click Filters and set Order Type to Unlocked. The date filter starts at today, which hides lines that started earlier.
  3. Click Batch Reschedule, and choose Forward Schedule or Backward Schedule.
  4. Set the one date that direction uses. Both dates start at today, not at the lines' own dates. Forward Schedule starts every line on the Work Start Date and sets its Ship Date to that date plus the line's labor days. Backward Schedule sets every line's Ship Date to the Ship Date and works the start back from it.
  5. Click Submit. Cetec shows Ordline schedule updated successfully and locks the lines.
  6. Check the result on the work orders' Schedule, as in Schedule the work order.