Change an order

Amend a live order — quantity, dates, revision, or lines — after it has been committed.

Updated Nov 5 2026

The order Edit screen is the classic screen for everyone. Unlike the order View screen, it has no React version, so the two can look like different generations of the product.

Who this is for

Sales reps and customer service make the change. Production planners and the warehouse live with it.

Applies to
Sales
Production
Inventory

Why it matters: an order line is a live work order, so a change reaches the shop floor the moment it is saved. It can move dates, change what is being built, and update linked purchase orders, and done carelessly it disturbs work already picked or in progress.

  1. What is changing

    1. Establish exactly what the customer or planner wants changed: quantity, dates, part, revision, adding a line, or something on the header such as shipping or billing details.
    2. Note whether it touches a Build line. A change to quantity, part, revision, or ship date on a Build line changes what production is scheduled to do.
  2. Find the order

    1. Click the magnifier (Global Search, or Ctrl+K) in the header and type the order number without its location prefix (121.1, not MN121.1), the customer's PO number, or the order name, then pick the order.
    2. Otherwise use the Order List (headed Orders) with the Cust PO or Order # filter under Filters. Sales > Orders > Order List
    3. From a customer, expand SALES + in the customer's left-hand menu and click ORDERS to list everything on the account. From a part, SALES > Orders lists every order containing it.
  3. Check what the change will disturb

    1. On the order's Edit screen, on a line with parts already picked, the quantity, the part, the revision, and a switch between Build and Stock are all locked. Each shows as text with a tip such as Qty change disabled while Parts are picked on this line. Unpick first, or make the change another way.
    2. Changing Qty Due, the part, the revision, or the Ship Date recalculates the line's work start date. If the work start date must stay where it is, click Disable Auto Fill before you make the change. It stays off for you on every order until you click Enable Auto Fill.
    3. Edit a line's Work Start Date by hand only if it should stay put. A hand-edited work start date is locked from automatic scheduling.
    4. If any line is linked to an internal PO, Cetec warns you that updating the order will also update the linked PO. Decide whether that is what you want before you save.
    5. If you are changing the order to Drop Ship, have the drop ship vendor ready. Cetec will not save the change without one.
    6. Check header changes are allowed. The order's location cannot change if the order is intercompany or drop ship, has closed lines, has a prepayment, or has a linked PO. The customer cannot change once the order has a prepayment.
    7. If you move Ship Date, check Dock Date too. It does not move with it. A customer with ship-ahead days shows a banner such as Note: Customer has Ship Ahead Days set to 7…. Keep the two dates that far apart.
    8. To see what changed before, open Sales > Orders > Bookings (open to Sales Managers). Cetec keeps a record of every change you save: each changed line gets a Modification entry with the old quantity, price, cost, part, and dates beside the new ones.
    9. If your instance has the Enable Order Change Log config on, History (called Order Change History on some screens) in the order's left-hand menu shows every earlier change to this order. The config is off by default. With it off, History still appears but lists only workflow stages.
  4. Edit the order

    1. Open the order and click Edit in its left-hand menu.
    2. To stop work on the order while a change is agreed, click Show Hold beside Submit, enter Hold Comments, tick Demand (keeps it out of MRP and allocation) and/or Production (stops it moving work location or being worked on), and click Place Hold. Invoicing is always held. The hold saves straight away, not with Submit. Cancel Hold releases it. Each line has its own Show Hold for holding one line.
    3. Change the header sections you need: Shipping Information, Billing / Sales Information, and the rest.
    4. Change the lines. Use Show/Hide All Advanced to open the advanced fields on every line at once, or the per-line Advanced toggle for one line.
    5. To add a line, click Add Line. Multi-level BOM lines can be added here too.
    6. To change a line's revision, pick it from the line's Revision dropdown.
    7. Click Submit for the section you changed. Cetec shows Success: Order Updated. Reopen View and verify the saved values. On a Stock line View shows the new ship date as Work Start Date; the Req Ship beside it is the original request and does not change. Tell Production and Warehouse when the change affects their work, and send a revised acknowledgement when customer-facing quantities, prices, or dates changed (Confirm the order with the customer).
    8. If the customer cancels, use Close Line/All in the order's left-hand menu. This is also where you delete an order. The screen, headed Delete Order {number}, offers Delete Selected Lines, Delete Order, and Delete Order & All Sub Orders, with confirmation. Close Line/All is disabled for users who cannot edit the order. If the order has a prepayment, deal with the prepayment first. That is Take a prepayment.
    9. To change what a Build line makes, go to the work order. This is usually done by production or engineering. Workorder View > Line {n}, click Use Old Version at the top (the new work order view has no Maint/Etc), then Maint/Etc. To move it to another revision use Change Rev. See Roll a revision onto orders. To change this order's own BOM or labor use BOM Management or Labor Plan Management. Cetec blocks BOM changes once components are picked: (Components have been picked, dekit first!)

Other ways to do this

Change many orders from a spreadsheet

For the same kind of change across many order lines: a batch of new ship dates, a price change, or a production line move. Sales > Orders > Order Mass Update

  1. Build a spreadsheet with the order number and line number on every row, plus the columns you are changing: dock date (Duedate), ship date, original ship date, target WIP date, production line, line comment, resale, first article, or your instance's bonus columns. Write dates as yyyy-mm-dd. Quantity, part, and revision are not in the list, so those still need the Edit screen, one order at a time.
  2. Open Sales > Orders > Order Mass Update (the screen is headed Import Order Data; up to 2,500 rows per import). Under Upload a New XLS/CSV Document choose the file, and click Import File. For a CSV that does not use commas, fill in CSV Delimiter first.
  3. Select the column type for each column and which rows to use, then click Update to check them. The grid is only a preview.
  4. Click Finish to apply the changes.
  5. Check a few of the orders afterwards rather than assuming every row went in. Cetec imports as much of the sheet as is valid.