Roll a revision onto orders
Move open work orders onto a new revision after a design change.Updated Nov 5 2026
Who this is for
Engineers move open orders onto a new revision once a design change is approved. Production planners and supervisors decide which orders can move and pick the material again for those that do.
Applies to
Why it matters: an approved change does nothing for orders already open — they keep building the old design until someone moves them. Moving one carelessly throws away changes made to that order's own BOM, or leaves its labor plan behind on the old revision.
-
Find the orders still on the old revision
- Open the design change's ECO (see
Change a design)
and scroll to
Open Orders For This Part. From a work order, the Part Is On ECO n link on the order's line opens it too. - Read each order's revision, dates and status. A revision with no name shows as a blank cell.
- Decide which orders move to the new revision and which finish on the old one. Making a new revision current never changes orders already open. Each one moves only when you move it.
- Open the design change's ECO (see
Change a design)
and scroll to
-
Check what the change will undo
- On each order's work order (
Maint/Etc > BOM Management), check whether anyone changed the order's own BOM — components added, removed or substituted on the work order. Moving the order rebuilds its BOM from the new revision and those changes are lost. - Check whether the order was committed with sub-assemblies built "with top". Those substitutions are lost too.
- Record any order-specific routing, times or work instructions that must be retained. The ECO roll can replace custom labor with the old revision's plan; it does not reliably import the new revision's routing.
- Check whether the order has parts picked or has been released to the floor. The
ECO can only roll orders that are still unreleased with nothing picked. An
order with picked parts or already released can still move, one at a time,
with
Change Revon the work order, as in Change one work order's revision under Other ways to do this. - Do these checks before the ECO ties the order with a
Productionhold, or lift the hold first.
- On each order's work order (
-
Roll the orders onto the new revision
- On the ECO's edit screen, check its saved
To Revis the intended destination. Save the ECO header withUpdateif you changed it; do not roll withTo Revunset. - In
Open Orders For This Part, tickRev Roll?on each approved order.Check All?under this column is separate from the one that ties orders; use it only after reviewing every affected row. Where the ECO cannot roll an order, the row says Unreleased Orders only! or Line has parts picked!. - Click
Updatein the orders section. - Open each rolled work order and check its revision and
BOM Managementcomponents against the new revision, including quantities per top and totals. A changed revision label alone does not prove that its BOM was rebuilt. - Roll every tied order before completing the ECO. The ECO cannot be completed while any order tied to it is still on the old revision.
- On the ECO's edit screen, check its saved
-
Update each order's labor plan
- Open each moved order's work order.
- Open
Maint/Etc > Labor Plan Management. It is hidden while the order has aProductionhold; the ECO's holds come off when you release them or when the ECO completes with auto-release. - Check the
Part Revision Labor Planlink points to the intended new revision. Compare the order's locations, operations, times and instructions with it. - Before replacement, preserve custom routing and completed instruction notes and coordinate rescheduling with production. The confirmation warns that completed instruction notes are lost, schedule records are cleared and sub-assembly labor does not transfer.
- Click
Replace Order Specific Labor Planand confirm when the order should use that revision's routing. Skip replacement only after confirming that the existing plan is the correct one. Restore any separately approved order-specific work afterward. - Verify the saved routing and instructions. Have production confirm the BOM, picks and routing agree before releasing the order or removing its holds.
Other ways to do this
Change one work order's revision
For a single order, or one that already has parts picked.
- Open the work order and choose
Maint/Etc > Change Rev(on the newer work view,BOM > Change Revin the left-hand menu). It is hidden while the order has aProductionhold, and you need permission to edit order BOMs to see it. - Unpick any serialized parts. Cetec refuses if serialized parts are picked, or if the new revision has no BOM.
- Check the current components, then choose the revision under
Existing Revisions. - Click
Change Revand confirm. Cetec dekits every part on the old revision and re-picks what it can onto the new one. - Cetec reloads the page without a success message. Check the saved revision
(in the work order header,
(Rev …)), BOM quantities and picks. Cetec re-picks only what it can, so resolve shortages before work resumes. - Review and update the labor plan, as in Update each order's labor plan.