Change a design
Change a product's design in a controlled way.Updated Nov 5 2026
Who this is for
Engineers raise and carry design changes. Production planners, buyers and quality review them and deal with the orders already in progress. Sales may be asked to requote.
Applies to
Why it matters: a design change decides what every future order builds. Done without control, the shop builds the old design after the new one was approved, or orders already in progress change underneath production with nobody accountable.
-
What is changing, and which orders it affects
- Know what changes: components, quantities, the labor plan, or the drawings.
- Know which revision the product is on now, and what the new one will be called.
- Know which open quotes and orders use the part. The ECO lists them for you once it exists.
- Decide what happens to orders already open: finish them on the old design, or move them to the new one. Completing the change only affects new quotes and orders. Orders already open stay on the old revision unless you move them with Roll a revision onto orders.
-
Create the new revision
- Open the part (
Parts > Lists > Part List, then the part) and clickRevisionsin the left-hand menu. - Type the new revision's name in
Create New Revisionand clickCreate. - Check
Current Rev?on both rows. Keep the approved revision current while the new design is under review. - Set the new revision's
StatustoPendingwhile it is under review, so nobody builds it early. Each revision has aStatus:Active,Pending,RunoutorObsolete. Only anActiverevision can be committed as a Build order; by default the others are refused at commit with … Is Set To {status} And Can Not Be Built!. Status saves as soon as you change it. - Open the new revision's
Edit BOMandLabor Plan. They can start as copies of the current revision, so review the inherited content as well as the edits. Use Define a BOM and Define a routing. Check drawings, reference designators and instructions for anything carried over incorrectly. - To see the differences between two revisions, use
Comparenext toEdit BOMon the newer Revisions page, orCOMPARE BOMin a revision's own left-hand menu on the classic one. Once the ECO exists, itsBOM Changessection shows the same comparison.
- Open the part (
-
Raise the ECO
- Open
Production > Orders > ECO/ECR List(the menu needs the Production role). Without it, start from the part'sQUALITY + > ECOS (n)menu item, which opens the same list for that part. - Click
Createon the newer list to openCreate New ECO/ECR(the classic list shows the form on the page). Select thePrcpart(it is not filled in for you, even from the part), choose theECO Type, and click the form'sCreate. Cetec opens the new ECO; check itsECO/ECR Typethere, as the choice may not carry over. - Choose the
From Rev((current)is the current revision) and theTo Rev. If the new revision doesn't exist yet,Add Revtakes you to the part's Revisions page. - Fill in the title and the reasons:
Reason For ChangeandDescription of Change. - Decide whether orders tied to this change should be held, and tick the
Order Hold Typeboxes:Shippingstops invoicing and shipping,Productionstops work and moves between work locations,Demandkeeps them out of MRP. TickingProductionorDemandalso turns onShippingwhen you save. Before you choose aProductionhold, check the affected orders as in Roll a revision onto orders. - Record what happens to the part's stock, shown as
Current QOHon the ECO, underDisposition—Rework,Return To Vendor,Use As Is,ScraporReturn To Stock. Cetec records the choice; it does not move the stock, so hand the work to the warehouse or quality. - For a regulated product, set
Regulated Application?toYesand fill inIf Regulated, Risk Mitigation. - Use
Affected Customer(s), which lists every customer who has ordered the part, for anyone who must be told. - Click
Update. Check the savedFrom RevandTo Revand the side-by-sideBOM Changes. A correct comparison confirms the target revision was saved.
- Open
-
Tie the affected orders to the ECO
- On the ECO's edit screen, scroll to
Open Orders For This Part. - Tick
Tie To ECO/ECR?underFrozen Pending ECO/ECR?on each affected order. UseCheck All?only when every listed order must move to the new revision; orders intended to finish on the old design must remain untied. - Click
Updatein that section. - Check the holds. Tied orders are tagged ECO and get the holds you chose. The
classic order view shows them in its
HoldandHold Commentcolumns (Hold added from freeze on ECO n). Untying an order removes the holds this ECO put on it. - Move the tied orders onto the new revision with
Rev Rollin the same section, as in Roll a revision onto orders. Before the ECO can be completed, every tied order must be on the new revision.
- On the ECO's edit screen, scroll to
-
Route it for approval
- On the ECO's edit screen, open the workflow control at the top (click the current stage or
Click to Open). Move the ECO to the appropriate review stage and choose its owner. Your company may have its own stages instead of the standard ones — engineering, purchasing, quality, document control and so on. - List the tasks that must be done under
Responsibilities And Requirements— tickRequired?on the ones that block completion — and assign each one. - As tasks are done, enter their
Completed Ondate. - As each stage signs off, the approver ticks
Approve?on that stage's row underApprovals. - Click
Updateto save requirements, owners, dates and approval checkboxes. - Watch
ApprovalsandECO Can Be Closed?to see what is still outstanding.
- On the ECO's edit screen, open the workflow control at the top (click the current stage or
-
Complete the ECO
- On the ECO's edit screen, check every tied order is on the new revision, every required task has a completed date, and every change is marked complete.
- To have the ECO lift its holds when it completes, open the newer ECO screen
(
Use New Version) and tickAuto-release holds when ECO is complete?before completing. Otherwise, release the holds on each order afterwards. - Choose
Complete ECO/ECRin the workflow control. It is listed only onceECO Can Be Closed?showsOK To Close? Yesand you may close ECOs. - Check the workflow stage now says
Completed. If the ECO stays in the same stage, its closure checklist is not satisfied or you lack permission. ReviewECO Can Be Closed?, required tasks and order revisions. A message naming the old stage is not proof of completion. - Open the part's
Revisionspage and verify that the intended new revision showsCurrent Rev?=Yes. - Set the revisions'
Status. Completing the ECO does not change any revision'sStatus: set the new revision toActiveif it is not already (aPendingrevision staysPendingand can't be built), and the old one toRunoutorObsoletewhen nothing more should be built on it. - Check the rolled orders' BOMs and labor plans with Roll a revision onto orders before handing them back to production.
Other ways to do this
Change a design on the Revisions page
For a change that needs no review, or when nothing open uses the old revision.
- Create the new revision and edit its BOM, as in Create the new revision.
- On the part's Revisions page, set
Current Rev?toYeson the new revision. It is aNo/Yesdropdown on both versions of the page and saves as soon as you change it. An obsolete revision cannot be made current. - Check that the old revision now says
No, and set each revision'sStatusas in Complete the ECO. - Open orders stay on the revision they had. Move them with Roll a revision onto orders.
Abandon the change
- Click
Cancel ECO/ECRat the top of the ECO. You need permission to close ECOs.