Define a routing
Define how a product is built, step by step, with time estimates.Updated Nov 5 2026
Who this is for
Engineers define how each assembly is built: where it goes, what is done there, and how long it takes. Production planners and supervisors work from the result — it becomes the traveler on the floor and the hours the schedule plans around.
Applies to
Why it matters: the routing is the labor estimate on every quote for the product and the order of work on every job. A missing step means work nobody planned for; a wrong time means quotes priced off the wrong labor and a schedule that never holds.
-
Check the work locations and operations exist
- Know the work locations the product passes through, in order — for example kitting, SMT, hand assembly, test, packing.
- Check each one exists. Work locations live in
Admin > Maintenance > Data Maintenance, underOrdline Status. A work location also needs its daily capacity before the schedule can use it. That is Set shop capacity. - Check each operation you will need exists, with its standard time. Operations
live in Data Maintenance too, under
Build Operations. An operation's standard time — seconds per piece, or pieces per hour — is set once on the operation, so every labor plan that uses it starts from the same time. - Ask your admin to add a location or an operation that is missing.
-
Open the revision's labor plan
- Open the part and click
Revisionsin the left-hand menu. If you are inside a revision already,LABOR PLANis in its left-hand menu. - Click
Labor Planon the row of the revision you are defining. Each revision has its own labor plan. Check the part and revision at the top; editing another revision will not change this one.
- Open the part and click
-
Add the work locations in build order
- On the revision's labor plan, choose a work location in the box below the
table (Search ordline status (location)... on the newer editor,
(add location)on the classic one) and clickAdd. - Repeat in the order the product moves through the shop. To add every location
your admin has given a build order, in that order, click
Add All Default Locationsinstead. - To change the order, drag a location row: by its
Ordercell on the classic editor, or by the handle at the left of the row on the newer one.Removetakes a location out, andRemove All Locationsclears the plan. - If the product has to wait before or after a location, such as a queue or a cure
time, enter it under
Bufferin the unit the header shows (for exampleBuffer (seconds): 30 minutes is 1800), choosePre(a wait before the work) orPost(a wait after it, such as curing), and clickSeton that row. Cetec applies the buffer when it schedules the location. On the classic editor, hoverBufferto see the unit.
- On the revision's labor plan, choose a work location in the box below the
table (Search ordline status (location)... on the newer editor,
-
Add the operations and their times
- On the revision's labor plan, click the pencil in a location's
Operationscolumn. - Choose an operation and click
Add. - Set
Timesif it happens more than once per unit. - Mark
Setupfor work done once per job regardless of quantity, and leave it off for work repeated for every unit. It is aYes/Nochoice on the classic editor and a checkbox on the newer one. Setup time is counted once in the estimate. Everything else is multiplied by the build quantity. - Click the operation's
Set. Check the savedTimes,Setupand total time, then repeat for each operation and location. - To reorder operations, use
moveon the classic editor or the arrows on the newer one. To delete an operation on the classic editor, tick itsDrop?and clickSet; the newer editor uses a trash icon.
- On the revision's labor plan, click the pencil in a location's
-
Write the work instructions
- On the revision's labor plan, click the pencil in the location's
Operationscolumn. The instruction block is below each operation, with a blank (new) row for a new instruction.Use Fancy Work Instructions, at the top of the page, switches to a rich-text editor with attachments. - Write what the operator must do and how to check success, including drawing references, measurements or inspection criteria where needed.
- Tick
Pick Req'dwhere material must be picked before work continues. Assign those components to the sameWork Locon the revision BOM; the requirement depends on that link. On the newer editor,Form - Pick Req'dis a different box, for custom forms. - Set
Sign Req'dwhere the operator must respond. The classic editor uses a checkbox. The newer editor offersResponse RequiredandResponse Required With Password. - Click the instruction block's
Update. This is separate from saving an operation's time. Check that the instruction remains after reopening it.
- On the revision's labor plan, click the pencil in the location's
-
Check the estimate and the traveler
- Open the revision's labor plan and read the totals at its foot:
Time Est,Setup,Recurring,Labor Est,Overhead EstandTotal, and the unit total time. Labor and overhead are priced from each work location's rates, so a location with no rate adds time but no cost. - Click
Preview Work List(it opens in a new tab) to check the traveler's revision, location sequence, operations and saved instructions. The revision shows only if it has a name. Confirm that someone new to the product can follow it without having to guess. - Check setup and recurring time against a realistic build quantity. For example, five minutes of setup plus two minutes per unit is twenty-five minutes for ten units. Have production review the estimate before release.
- Plan for orders already committed. They normally use their own copy of the
plan. Revision rolling can rebuild that copy; see
Roll a revision onto orders.
To change one work order's plan, open the work order and use
Maint/Etc > Labor Plan Management.
- Open the revision's labor plan and read the totals at its foot:
Other ways to do this
Set one total labor estimate
For a product that needs a labor estimate but not a step-by-step routing.
- Open the revision's labor plan, as in Open the revision's labor plan.
- Under
Total Labor Estimateat the bottom, chooseUse Total Labor Estimate. The minutes box stays greyed out until you do. - Enter the total in minutes and click
Update. The total applies to every revision of the product, and Cetec then ignores the location plan — the page says so. - To go back, choose
Use Location Path Estimateand clickUpdate. That clears the total to 0.
Start from another plan
- On the revision's labor plan, use
Copy Labor From Another RevisionorCopy Labor From Another Part. - To share another revision's plan instead of copying it, use
Link Labor To Master Part Revision.
Build the plan from the components
Where your parts carry default labor operations.
- On the revision's labor plan, tick
Allow Labor To Be Set From Components?underOther Maintenance(Other Labor Maintenanceon the classic editor). While the box is ticked,Use Total Labor Estimateis disabled. - Use
Repopulate From Components?andGo. They overwrite the plan with one compiled from each component's labor and switch the revision to the location path estimate.