Define a routing

Define how a product is built, step by step, with time estimates.

Updated Nov 5 2026

Who this is for

Engineers define how each assembly is built: where it goes, what is done there, and how long it takes. Production planners and supervisors work from the result — it becomes the traveler on the floor and the hours the schedule plans around.

Applies to
Engineering
Production

Why it matters: the routing is the labor estimate on every quote for the product and the order of work on every job. A missing step means work nobody planned for; a wrong time means quotes priced off the wrong labor and a schedule that never holds.

  1. Check the work locations and operations exist

    1. Know the work locations the product passes through, in order — for example kitting, SMT, hand assembly, test, packing.
    2. Check each one exists. Work locations live in Admin > Maintenance > Data Maintenance, under Ordline Status. A work location also needs its daily capacity before the schedule can use it. That is Set shop capacity.
    3. Check each operation you will need exists, with its standard time. Operations live in Data Maintenance too, under Build Operations. An operation's standard time — seconds per piece, or pieces per hour — is set once on the operation, so every labor plan that uses it starts from the same time.
    4. Ask your admin to add a location or an operation that is missing.
  2. Open the revision's labor plan

    1. Open the part and click Revisions in the left-hand menu. If you are inside a revision already, LABOR PLAN is in its left-hand menu.
    2. Click Labor Plan on the row of the revision you are defining. Each revision has its own labor plan. Check the part and revision at the top; editing another revision will not change this one.
  3. Add the work locations in build order

    1. On the revision's labor plan, choose a work location in the box below the table (Search ordline status (location)... on the newer editor, (add location) on the classic one) and click Add.
    2. Repeat in the order the product moves through the shop. To add every location your admin has given a build order, in that order, click Add All Default Locations instead.
    3. To change the order, drag a location row: by its Order cell on the classic editor, or by the handle at the left of the row on the newer one. Remove takes a location out, and Remove All Locations clears the plan.
    4. If the product has to wait before or after a location, such as a queue or a cure time, enter it under Buffer in the unit the header shows (for example Buffer (seconds): 30 minutes is 1800), choose Pre (a wait before the work) or Post (a wait after it, such as curing), and click Set on that row. Cetec applies the buffer when it schedules the location. On the classic editor, hover Buffer to see the unit.
  4. Add the operations and their times

    1. On the revision's labor plan, click the pencil in a location's Operations column.
    2. Choose an operation and click Add.
    3. Set Times if it happens more than once per unit.
    4. Mark Setup for work done once per job regardless of quantity, and leave it off for work repeated for every unit. It is a Yes/No choice on the classic editor and a checkbox on the newer one. Setup time is counted once in the estimate. Everything else is multiplied by the build quantity.
    5. Click the operation's Set. Check the saved Times, Setup and total time, then repeat for each operation and location.
    6. To reorder operations, use move on the classic editor or the arrows on the newer one. To delete an operation on the classic editor, tick its Drop? and click Set; the newer editor uses a trash icon.
  5. Write the work instructions

    1. On the revision's labor plan, click the pencil in the location's Operations column. The instruction block is below each operation, with a blank (new) row for a new instruction. Use Fancy Work Instructions, at the top of the page, switches to a rich-text editor with attachments.
    2. Write what the operator must do and how to check success, including drawing references, measurements or inspection criteria where needed.
    3. Tick Pick Req'd where material must be picked before work continues. Assign those components to the same Work Loc on the revision BOM; the requirement depends on that link. On the newer editor, Form - Pick Req'd is a different box, for custom forms.
    4. Set Sign Req'd where the operator must respond. The classic editor uses a checkbox. The newer editor offers Response Required and Response Required With Password.
    5. Click the instruction block's Update. This is separate from saving an operation's time. Check that the instruction remains after reopening it.
  6. Check the estimate and the traveler

    1. Open the revision's labor plan and read the totals at its foot: Time Est, Setup, Recurring, Labor Est, Overhead Est and Total, and the unit total time. Labor and overhead are priced from each work location's rates, so a location with no rate adds time but no cost.
    2. Click Preview Work List (it opens in a new tab) to check the traveler's revision, location sequence, operations and saved instructions. The revision shows only if it has a name. Confirm that someone new to the product can follow it without having to guess.
    3. Check setup and recurring time against a realistic build quantity. For example, five minutes of setup plus two minutes per unit is twenty-five minutes for ten units. Have production review the estimate before release.
    4. Plan for orders already committed. They normally use their own copy of the plan. Revision rolling can rebuild that copy; see Roll a revision onto orders. To change one work order's plan, open the work order and use Maint/Etc > Labor Plan Management.

Other ways to do this

Set one total labor estimate

For a product that needs a labor estimate but not a step-by-step routing.

  1. Open the revision's labor plan, as in Open the revision's labor plan.
  2. Under Total Labor Estimate at the bottom, choose Use Total Labor Estimate. The minutes box stays greyed out until you do.
  3. Enter the total in minutes and click Update. The total applies to every revision of the product, and Cetec then ignores the location plan — the page says so.
  4. To go back, choose Use Location Path Estimate and click Update. That clears the total to 0.

Start from another plan

  1. On the revision's labor plan, use Copy Labor From Another Revision or Copy Labor From Another Part.
  2. To share another revision's plan instead of copying it, use Link Labor To Master Part Revision.

Build the plan from the components

Where your parts carry default labor operations.

  1. On the revision's labor plan, tick Allow Labor To Be Set From Components? under Other Maintenance (Other Labor Maintenance on the classic editor). While the box is ticked, Use Total Labor Estimate is disabled.
  2. Use Repopulate From Components? and Go. They overwrite the plan with one compiled from each component's labor and switch the revision to the location path estimate.