Set shop capacity

Define what the shop can do in a day.

Updated Nov 5 2026

Who this is for

Production managers and schedulers tell Cetec how many minutes of work each work location can do in a day. Engineering owns the labor plans that use that capacity.

Applies to
Planning
Production
Engineering

Why it matters: Cetec can only schedule against capacity it knows about. Without capacity on your work locations, the Planning Gantt Chart shows no schedule at all.

  1. Set the base capacity of each work location

    1. Ask your admin to open the work location table: Admin > Maintenance > Data Maintenance, then the OrdlineStatus row. The table is titled Data Maintenance For OrdlineStatus, with one row per work location (its Description).
    2. For each work location, set Capacity Minutes Per Day, and the Labor Rate and Overhead Rate if they aren't set. The rates also drive what a job costs. See Compare job cost to estimate.
    3. To add a work location, click Add Record. Cetec saves an empty row at once (default 480 minutes); type its Description.
    4. Click Submit at the bottom. It saves the whole table, and Cetec shows no message.
  2. Adjust capacity by date

    1. Open Production > Scheduling > Set Capacity. The page is titled Set Production Capacity and shows a month. Only managers and supervisors can open the scheduling screens.
    2. Click a date. In Edit Capacity For {date}, set the Capacity Minutes and # Users for each Location that differs that day, and add Notes. To close a location for a holiday, set Capacity Minutes to 0. # Users can't go below 1: a 0 changes back to 1 when you leave the box.
    3. Click Update. Cetec shows Update Successful and saves every row in the window. The window stays open; close it with Cancel or the X.
    4. To repeat a day or a week, use Copy Capacity From Date Range: pick the Warehouse Locations, the From and To date ranges, and click Copy Capacity. Cetec shows Copy Capacity Successful. It copies every work location in the warehouses you pick. Work locations are tied to a warehouse by the Location column of the work location table.
    5. To put dates back to the base capacity, click Reset Capacity. In Reset Capacity To Defaults, pick the Work Location and the Date Range, and click Reset.
  3. Check how loaded the shop is

    1. Open Production > Scheduling > Capacity Utilization.
    2. Choose View By (Day, Week or Month) and the Date Range, and click Submit.
    3. Compare Scheduled with Capacity for each location and date.

Other ways to do this

Open the work location table from Set Capacity

  1. On Production > Scheduling > Set Capacity, click Reset Capacity. The Reset Capacity To Defaults panel also shows a Set Base Capacities button that opens the same work location table.