Define a BOM
Define what a product is made of.Updated Nov 5 2026
Who this is for
Engineers define what each assembly is made of. Buyers, production planners and the warehouse work from the result: it is what gets bought, picked and built for every order of that product.
Applies to
Why it matters: the BOM drives material cost on quotes, what purchasing orders, and what the shop picks. A missing component or a wrong quantity per unit means shortages on the floor or a cost that never matched the price.
-
What the product is made of
- List the components and how many of each go into one unit.
- Mark which components are themselves assemblies. Each one needs its own BOM, defined before the product that uses it. Cetec refuses a component it cannot find as a part, so build a multi-level BOM from the bottom up: the lowest sub-assembly first, the finished product last.
- Check every component exists as an active part in Cetec. Set up missing parts with Set up a part before adding them.
- Check the units: a quantity is in the component's stock UOM, per one finished
assembly. For example, two screws per assembly is
Qty Per Top=2; an order for ten assemblies needs twenty screws before scrap allowances.
-
Create the BOM part
- Open
Parts > Lists > Part Listand clickCreate Part(Create Newon the older list). - Pick the
PRC, type thePartnumber, check theLocation, and add aPart Description. ThePRCis the three-letter product code the part belongs to. Many companies keep one, such asBOM, for assemblies. - Tick
BOM?, and give the first revision a name inRevisionif you want one (for exampleA). - Click
Create. Cetec opens the new revision'sEdit Revision BOM. Check the part number and revision at the top before adding components. - Open the part's
Editprofile and check its stockUOMbefore the part is quoted or stocked. A new part may have no UOM until you set one. Save withUpdate. - Return to this revision's
Edit BOM: open the part, clickRevisions, and clickEdit BOMon the revision's row. Use the same path whenever you come back to the BOM later.
- Open
-
Add the components
- On the revision's
Edit Revision BOMscreen, in theAdd new componentrow below the list, enter the component's part number underPrcpartand itsQty Per Top— how many go into one unit — plusWork LocorReference Designatorif you use them. LeaveComp #at 0 and Cetec numbers the lines for you. - Click
Addon the newer editor. Check that the component appears as a saved row before adding the next one. The classic editor adds its footer row when you clickUpdate. - Fill in any other columns you need on the added rows —
Scrap Factor,Scrap Adder,Comments,Pick Comments,Sourcing— and clickUpdate. The table is wider than the screen: scroll it to the right to reachQty Per Top, the later columns, and theUpdatebutton at its bottom right. - Enter scrap the way Cetec reads it.
Scrap Factorgrows with the quantity:5means five extra per assembly, so two per assembly with a scrap factor of 5 needs seven;5%means five percent extra.Scrap Adderis a fixed extra for the whole build. Both start from the component part's defaults, set on its profile. - Check that the saved quantities and reference designators match your drawing;
typing into a row does not save it until you click
Update. - To pin a sub-assembly to one of its revisions, set the line's
Revision. Otherwise it always uses the sub-assembly's current revision. - To remove a line, click the red ✖ under
Info/Deleteon its row — the row highlights — then clickDeleteat the bottom right of the table and confirm.
- On the revision's
-
Check the BOM
- Open the part and click
BOM DATA > BOM Overview. - Confirm which revision the overview is showing — it says BOM Overview for
Current Revision above the list. Check the structure level by level in the
component tree at the top;
Expand / Collapse Treeopens every level (Show/Hide Tree View of BOMon the older screen). - Read any warning about components with no part record, and fix them.
- Enter a
Build Qtyand clickSetto see what the whole BOM costs at that quantity. Compare the extended quantities with your expected build. - Say which material cost you mean when you hand a cost to Sales. The BOM
Overview's material cost can differ from
Material Costat the foot ofEdit Revision BOM. The editor uses each component's own cost; the Overview rolls sub-assembly costs up from their BOMs, shown in itsRollupcolumn. - To follow quantities through the levels, use
BOM DATA > Build w/ Subs, which walks the build quantities down through the sub-assemblies.BOM DATA > BOM Use (n)lists every BOM a part is on. The older screen hidesBOM Useon a part no BOM uses. - Attach drawings to the revision, not the part, when they belong to one
revision: open the revision and use its
Documentsmenu item. Documents attached to the part are not tied to any revision. - Before handing off to quoting or production, check the component list, units, quantities, sub-assembly revisions and drawings together. Saving a BOM does not mean the design has been approved for release.
- Define how the product is built — work locations, operations and times — with Define a routing. To change a released BOM in a controlled way, use Change a design.
- Open the part and click
Other ways to do this
Turn an existing part into a BOM
The part already exists in Cetec.
- Open the part and click
Edit. - Click
Create As BOMin General Information. - Continue at Add the components.
Start from another BOM
- On the revision's
Edit Revision BOM, clickShow Copy from BOM/Rev. - Choose the BOM and revision, and click
Overwrite/Copy. It replaces every component already on this revision, so use it before you add your own, not after.
Add many components at once
- To paste a list, click
Show Batch Component AddonEdit Revision BOMand paste the components in. - To load components from a spreadsheet, use
IMPORT BOMin the revision's left-hand menu.