Track a job through the shop

Know where a job is and move it to its next step.

Updated Nov 5 2026

Who this is for

Operators and leads move work orders from one work location to the next as the work is done. Supervisors and schedulers read the work order's location to see where every job stands.

Applies to
Production
Quality
Planning

Why it matters: a work order's location is its status. If jobs aren't moved when the work moves, nobody can tell what is late, what is waiting, or what is ready to ship.

  1. Find the work order

    1. Open Production > Orders > Production Order List.
    2. Click Filters, pick your location under Work Location, and click Apply.
    3. Click the Work Start Date heading to work the jobs in order.
    4. Click the order number to open the work order.
  2. Finish what the location requires

    1. On the work order's Work view, check for a red Location Locked Pending Work Instr and Material Pick of: message under Move Location. It lists what is still missing.
    2. For each required work instruction, click view here (or open the work order's Instructions), type the response, and save it. An instruction marked Response Required With Password asks for your password as a signature.
    3. For parts still to pick, pick them (Pick material for a job).
  3. Move the job to its next location

    1. On the work order's Work view, under Move Location, click Move To Next. Hover over it to see which location is next.
    2. To send the job somewhere other than the next step, pick the location from the list, then click Move To Next. The list only offers the locations on this job's labor plan; users with permission see See All to choose any location. Cetec warns The selected location is not the next location in the labor plan and names the next one; click Yes if that is what you meant.
    3. To move only part of the quantity ahead, click Partial Move, pick the Location, type the Quantity To Move, and click Submit. The job itself stays where it is. If the Partial Move location list is empty, use Partially move here on the newer Work view instead (see Other ways to do this).
    4. If your shop schedules to finite capacity, tick the unlabelled checkbox next to Partial Move to mark this location's schedule entries complete. That frees the capacity for other jobs.
    5. Confirm Cetec shows Location Changed to {location}.
    6. When the last step is done, finish the build (Finish a build).

Other ways to do this

Open the work order another way

Open a work order from your pick queue or the search box instead of the Production Order List.

Move from the newer Work view

  1. On the newer Work view, click Move Location (the classic view's Move To Next).
  2. To move to a specific location, open that location's ... menu and click Move to this location.
  3. To move part of the quantity, open the location's ... menu and click Partially move here.