Expedite open purchases

Track whether vendors will deliver on time.

Updated Nov 5 2026

Who this is for

Buyers chase vendors for confirmations and dates. Production planners need the answers to know whether a job will start on time.

Applies to
Purchasing

Why it matters: a PO nobody confirmed is a guess. Finding out a part is late on the day it was due is the most expensive time to find out.

  1. Find the POs at risk

    1. Open Purchasing > POs > Purchase Order List. The screen is headed Purchase Orders.
    2. Click Filters, set Acknowledged? to No, and click Apply. On the older Purchase Order List, these filters are under More Options and the button is Submit.
    3. Look down the Acknowledged column for blanks too. A PO nobody has marked either way shows blank and is not caught by No.
    4. For lateness, set View By to PO Line, set Days Early to < and Days Early Value to 0, and click Apply.
    5. Save these as bookmarks. They are the expediting list you will run every week.
  2. Check which jobs are waiting on them

    1. On the Purchase Order List, with View By set to PO Line, read Days Early on each line. Negative means it lands after the order it is for needs it, positive means early.
    2. Read Suggestion beside it: Pull In, or Cancel.
    3. Check Need Date. A line with no need date has no order waiting on it, and shows Days Early 0. Do not read that as on time.
    4. To see the jobs that are short and the PO covering each shortage, open Production > Orders > Order Material Report and click Submit. You need access to production screens for this report.
  3. Ask the vendor to confirm

    1. Contact the vendor about the late or unconfirmed POs.
    2. To resend a PO, open it, click PDF/Email in its left-hand menu (PDF/Export on the older screen), then Email PO.
  4. Record the vendor's answer

    1. Open the PO and click Acknowledge in the left-hand menu.
    2. Set PO Acknowledged? to Acknowledged.
    3. Add the vendor's comments for the whole PO in Comments.
    4. Add any tracking numbers per line, or tick Add To All Lines Needing Tracking #, and click Add.
    5. Click OK. Cetec confirms the tracking numbers with Success: Tracking Numbers Added!, and the acknowledgement saves with them.
    6. If the vendor gives a new dock date or quantity, change the PO too. See Change a purchase order.
    7. To be told when the PO is received, use Notifications on the PO. On the newer screen it is under Utilities.

Other ways to do this

From the Purchasing dashboard

If your home page uses the Purchasing dashboard, its widgets show late POs and acknowledgements.

Vendors acknowledge in the portal

Vendors with portal access can acknowledge their own POs.