How To Manage Revisions Using the ECO Process
An ECO (engineering change order, or ECR for a request) moves a part from one revision to the next under control: it records why the change is made, which open orders it affects, who must do what, and who approved it. Completing the ECO makes the new revision the part's current revision.Updated Nov 9 2026
Before you start
- Production > Orders > ECO/ECR List needs the Production role. Without it, open the part's QUALITY > ECOS (n) in its left menu, which opens the same list for that part.
- Editing an ECO and completing or cancelling it need ECO permissions; without them the ECO shows No Edit Permissions For This ECO/ECR!.
- The ECO opens on the new ECO screen if you have chosen it before. If it opens on the classic screen, click Use New Version on it.
-
Create the ECO
- Go to Production > Orders > ECO/ECR List (the page is headed ECO/ECR List).
- Click Create at the top of the list. The Create New ECO/ECR window opens.
- In Prcpart, type the part number and pick the part from the suggestions.
- Choose the ECO Type (such as Customer Driven), and click Create. Cetec opens the new ECO, headed ECO/ECR and its number.
-
Set the revisions and describe the change
- On the ECO, check From Rev. It starts on the part's current revision.
- Choose the revision to change to in To Rev. If the new revision doesn't exist yet, click Add Rev. The part's Revisions page opens in the same tab: type the new revision in Create New Revision, click Create (Cetec shows New Revision Created.), then go back to the ECO with your browser's Back button and choose it in To Rev.
- Fill in Title, Reason For Change and Description of Change. There is also a Comments box for the workflow stage the ECO is in (for example ECO/ECR Initiator Comments) for notes from that stage.
- Set Disposition for the stock on hand (shown as Current QOH), and Regulated Application? with If Regulated, Risk Mitigation if it applies.
- Under Order Hold Type, tick the holds tied orders should get: Shipping (no invoicing or shipping), Production (no work or moves between work locations), Demand (left out of MRP and allocation, and hidden on the waterfall). Ticking Production or Demand turns on Shipping as well: the Shipping box ticks itself when you click Update in the next step.
- Click Update under the comment boxes. Cetec shows Eco updated Successfully. BOM CHANGES now compares the two revisions' components side by side. A new revision starts with no BOM, so its side stays empty until its components are added.
-
Tie open orders and roll their revision
- On the ECO, scroll to Open Orders For This Part. Each open order for the part is listed with its Revision, Location, WIP Date and Ship Date. Open Quotes For This Part above it lists open quotes.
- In Frozen Pending ECO/ECR?, tick Tie To ECO/ECR? on each order this change affects. Tied orders get the holds chosen under Order Hold Type. Leave orders that should finish on the old revision unticked. An order line already tied to an earlier ECO on the same part can show as ticked here before you touch it.
- In Rev Roll, tick Rev Roll? on each order to move onto the To Rev. Only orders that are still unreleased with nothing picked can roll; the others say Unreleased Orders only! or Line has parts picked!. Check All? at the top of each column ticks every row. As the warning in the table says, order-specific BOM changes and Build With Top substitutions on a rolled line are lost.
- Click Update in that section. Cetec shows Open Orders updated Successfully. A rolled order now shows the new Revision and who set it; its Rev Roll? tick clears. The line under the table says whether All Linked Orders Have Correct Revision.
-
Assign responsibilities and approve
- Under Responsibilities And Requirements, each Task has an Ownership box: type part of a user name and choose who does it. Tick Required? on the tasks that must be done before the ECO can close, and enter Completed On when a task is done. Click Update in that section. Cetec shows Requirements updated Successfully.
- Under Approvals, the person for each Stage ticks Approve? and clicks Update. Cetec shows Approvals updated Successfully and fills in Approved On and Approved By.
- Move the ECO through its review with the workflow control at the top right of the ECO. It shows the current stage and its owner (for example ECO/ECR Initiator: …). Click it to open the workflow panel, and under Move To click the next stage (such as Quality). Cetec shows Successfully changed transition, and the new stage gets its own Comments box and Approvals row. To close the panel without moving the ECO, click its heading again.
-
Complete the ECO
- Check ECO Can Be Closed? at the bottom of the ECO: each check (such as Open Orders OK? and Responsibilities and Requirements OK?) shows Yes or No.
- To have Cetec lift the holds on tied orders when the ECO completes, tick Auto-release holds when ECO is complete? (next to Order Hold Type) and click the Update under the comment boxes.
- Open the workflow control at the top right and, under Move To, click Completed. The To Rev becomes the part's current revision, and the banner then reads Completed on … By …. Cetec doesn't wait for every stage's approval, so check Approvals first.
- Click View Part at the top of the ECO (it opens the part's page in the same tab), then Revisions in the part's left menu. Set each revision's Status as needed (for example the new one to Active, the old one to Obsolete): a status saves as soon as you choose it. Completing the ECO doesn't change them.