Raise a purchase order

Order material from a vendor.

Updated Nov 5 2026

Who this is for

Buyers raise purchase orders. Production planners and the warehouse depend on them: the PO is what makes material arrive in time for the job, and what receiving checks deliveries against. Accounting matches the vendor's bill to it.

Applies to
Purchasing

Why it matters: a late PO means a late job, and a wrong one means the wrong material, the wrong price, or a bill that won't match.

  1. What you are buying, from whom, and by when

    1. Know the parts and quantities, the vendor, and the date you need them on your dock.
    2. Know which warehouse location receives them.
    3. Know whether a cost center is needed. Your admin may require one.
    4. Most POs start from a buy signal in MRP (see Plan what to buy) or from a sales order that needs material. Both end up on this same path.
  2. Start a PQuote

    1. Open Purchasing > PQuotes > PQuote List and click Create once. A PQuote is a draft PO and a request for quote in one, and every PO starts as one. There is no New PQuote menu item; the list's Create button is the way in. Cetec opens a new PQuote, titled PQuote / PO Worksheet with its number. Your default location is already filled in.
    2. Or, from any page, click Create > Start Purchase Order in the header, choose the vendor, and click Create.
  3. Fill in the vendor and the lines

    1. On the PQuote, click the pencil at the top left of the header. In the Edit Header Information window, type the vendor's name in Vendor and pick it from the results, check the location, set the cost center if your company uses them, and click Ok. Picking the vendor fills in its terms.
    2. In the row at the bottom, enter the quantity, search for the part and pick it, check the dock date (it starts at today) and the cost, and click Add. Cetec fills the cost in as soon as you pick the part, from the vendor's price breaks or what you last paid (see Record vendor pricing). Type over it only if the price is different. Repeat for each line.
    3. Compare each line's cost against standard (PPV) and what you last paid (LBV). PPV and LBV compare against the part's standard cost and last buy cost. A new part with no standard cost shows the full price as PPV and 0.00%. That's not an error.
    4. Expect a non-inventory part to be flagged Non-Inventory? automatically. The flag can't be changed, and the part won't create stock when received.
    5. To change a line, click its pencil. To delete one, click the red X, then Delete at the bottom right.
  4. Read what blocks the PO

    1. On the PQuote, click Convert to PO in the left-hand menu.
    2. If Cetec lists reasons the PQuote can't become a PO, fix each one on the PQuote and come back.

    The reasons you may see:

    • Not Open or No Open Lines: nothing left to order.
    • No Vendor, No Location: set them in the header.
    • No Cost Center or Line with no Cost Center: your admin requires them.
    • Line with no Part: a line has no part number.
    • Manufacturer Part Required: pick the manufacturer part on the line.
    • Vendor Is On Hold!: the vendor must be released first (see Set up a new vendor).
    • Not Approved: it needs approval (see Get a purchase approved).
  5. Place the purchase order

    1. On the Convert to PO screen, check the PQuote one last time.
    2. Click Place Purchase Order. Cetec places the PO and opens it. It takes both clicks, Convert to PO and then Place Purchase Order. Stopping after the first leaves you with no PO.
    3. To find the PO again later, open it from its PQuote, or from Purchasing > POs > Purchase Order List.
  6. Send the PO to the vendor

    1. On the new PO, click PDF/Email in the left-hand menu (PDF/Export on the older screen). Placing the PO sends nothing to the vendor by itself.
    2. Click Email PO. Fill in From and check To, and click Send. Cetec says PDF sent, notes who it went to, and marks the PO emailed in the Purchase Order List.
    3. To send the file yourself, click Download PDF instead. The PO then isn't marked emailed.
    4. Tracking whether the vendor confirmed the PO and will deliver on time is covered in Expedite open purchases.

Other ways to do this

Buy for one sales order

For material bought specifically for a customer's order. You need access to sales orders to do this.

  1. Open the sales order and click Create PQuote in the left-hand menu.
  2. Set the quantity for each part, or click Set Qty Need for All Parts.
  3. Tick Pre-Allocate these Parts to this Customer? to tie the incoming material to this customer, and Use order cost instead of default cost? if you want the order's costs carried over.
  4. Choose the vendor, leave the dropdown on (Leave Blank to Create New) or pick an existing PQuote, and click Submit.
  5. Open the PQuote and continue at Fill in the vendor and the lines. This makes a PQuote, not a PO. You still convert it and place it.