Plan what to buy

Determine what material to buy or build, and when.

Updated Nov 5 2026

Who this is for

Buyers use MRP to see what to buy and when. Production planners use it to see which sub-assemblies to build.

Applies to
Purchasing
Production

Why it matters: MRP is how open orders become buys on time. Skip it and material arrives late. Trust it with stale data or wrong lead times and you buy too early, too much, or the wrong thing.

  1. Choose what you are planning

    1. Open Purchasing > MRP and pick one. All three open the same screen with different filters set.
      • MRP - Buy: parts bought from vendors.
      • MRP - Build: sub-assemblies built in-house.
      • MRP - All: both.
  2. Check lead times and reorder points

    1. Check the parts you buy have a lead time, and a reorder point (ROP) if you keep them in stock.
    2. To set them, open the part (Parts > Lists > Part List, then click it). On its View screen find WAREHOUSE SPECIFIC DATA FOR the location and click the pencil. Lead time and ROP are set per warehouse on the part's View screen, not on its Edit screen, so the same part can have a different ROP in each warehouse.
    3. Enter Lead Time (days) and ROP, scroll down inside the window, and click Update.
  3. Check how current the data is

    1. On the MRP screen (Purchasing > MRP), read the timestamps at the top: when allocation last ran, when MRP was last refreshed, and whether forecasts were included.
    2. A refresh is only as current as the last allocation run. If allocation ran long ago, ask your admin before relying on the numbers.
  4. Refresh MRP and read the signals

    1. On the MRP screen (Purchasing > MRP, headed MRP Requirements), choose Standard Mode. It gives need dates for buys driven by orders. Lite Mode is faster but only says whether to buy, not when.
    2. Click Refresh. Cetec says the refresh is queued. The page reloads itself when it's done and the timestamp under the heading updates. Your MRP results are your own. A colleague refreshing MRP doesn't change yours.
    3. Filter by Prcpart (the part number), Vendor, Location or Source Type, and click Submit. Source Type separates buys driven by orders (Supply/Demand) from buys driven by reorder points (ROP). Order # is under More Options.
    4. Read each line: QOO (on order), QOH (on hand), Avail, Sum Req'd Qty (the quantity to buy, which you can change before acting) and Aging Buy Signal (Days), how long the signal has waited. A reorder-point line has no need date or buy date. It only says the stock is below its ROP.
  5. Check the supply and demand behind a signal

    1. On the MRP screen, click the Avail value on a line to open the part's waterfall.
    2. Read demand on the left and supply on the right, by location, and find where the projected quantity goes negative. That date is when you run out.
    3. To see every line's waterfall on the page at once, set Expand All Part Info? to Waterfall Only.
  6. Turn the signals into PQuotes or work orders

    1. On the MRP screen, tick the lines you want to act on. To hide signals you won't act on, tick them and click Ignore Checked Lines.
    2. To buy: leave the dropdown on (Leave Blank to Create New PQuote) or pick an existing PQuote, enter a vendor or leave it blank to use each line's vendor, and click Add/Create PQuote. Cetec takes you straight to the new PQuote. Place it as in Raise a purchase order.
    3. To build: pick an existing worksheet or start a new one, choose the internal customer, and click Add/Create Quote/Order Wksht. Then commit it as in Turn a quote into an order.
    4. To find POs that arrive too early, click Review POs. It opens a PO list filtered to lines more than 14 days earlier than the orders they are for, candidates to push out or cancel. Click Submit to fill it. To change them, see Change a purchase order.

Other ways to do this

Create PQuotes for every vendor at once

On the MRP screen, click Auto-Create PQuotes. It makes one PQuote per vendor from all the signals.