Who this is for

Buyers and production planners send steps such as plating, heat treat or welding to outside processors. Accounting pays the processor's bill.

Applies to
Purchasing
Production

Why it matters: an outside step is where jobs disappear from view. Without a PO tied to the job, nobody knows it's out, when it's due back, or what it cost.

  1. Which step goes outside, and to whom

    1. Know the work order, the service (for example plating), the processor, and when you need it back.
    2. Check the service exists as a part. Search for it as you would any part number. If it doesn't exist, have it set up first (see Set up a part).
  2. Check the work order can be outsourced

    1. Open the work order: Production > Orders > Production Order List, then click the order line. Its screen is headed Workorder with the line number.
    2. Click Outsource PO in the work order's header.
    3. If Cetec says the line needs a cost center, set one on the order line first. Your admin requires it.
  3. Create the outsource PO

    1. Under Create new PO for Vendor, search for the processor and pick it. The location is the work order's own.
    2. In the line, enter the service part under Prcpart.
    3. Set Qty. It starts at 1, not the work order's quantity. Tick Lock Qty To Line to tie the PO quantity to the work order's.
    4. Enter the Dock Date and Cost. Cetec fills the cost from the part's price after you pick it, and may replace a cost you typed quickly, so check the cost and dock date just before you click.
    5. To add to an outsource PO you already have, fill in OR add to PO instead.
    6. Click Create Outsource PO. Cetec places the PO straight away and says PO {number} Created!
    7. The outsource POs for this work order are listed on its Outsource PO screen. View All Outsource POs opens the outsource POs across all orders.
  4. Send the work and track it

    1. Send the material to the processor with the PO.
    2. On the work order, use Move Location to move it to its outsourcing work location (for example At Vendor Outsourcing) so the shop can see it's out. See Track a job through the shop.
  5. Receive the work back

    1. When the work comes back, receive the outsource PO line like any other PO line. See Receive material.
    2. Move the work order on to its next step.